Planned Works June/July

  • Installation of pipework and electrical equipment in risers continue
  • Level 11 blockwork continues
  • West core demolition commenced
  • Waterproofing level 11 commenced
  • Removal of temporary steelwork continues
  • Dry lining to rooms continue
  • Screeding to level 9 commenced
  • Cladding to upper levels
  • Core drilling throughout the floor for services penetrations