Progress Update

We have now finished the demolition of the C-Shape wall.  As reported in previous editions, the C-Shape wall has been constructed along with extra perimeter steelwork to help support the new steelwork on the roof.

Planned works December/January

  • Goods lift works continues
  • Hoist & hoist Landing January 2017
  • Roof extension work continues
  • Screeding to 8th floor terraces continues
  • Concrete pour to level 10 January 2017
  • Scenic lift works continues

Green Card Award

Health & Safety is a big part of construction life and here at McLaren we like to award those who go that extra mile in reporting near misses and suggestions. This month the Green Card Award was given to the Wellmax Scaffolding operative, Javan Clarke along with £50 John Lewis vouchers by our Site Manager Christiaan Steyn.

Christmas Shutdown

The site will be closed for the Christmas shutdown from Friday 23rd December 2016 and will re-open on Tuesday 3rd January 2017.

 

From all at McLaren we would like to wish all our neighbours a very Merry Christmas and a Prosperous New Year!!!