Tonbridge Walk Closures

 

  • Due to the scaffolding on the West elevation being removed, McLaren have applied for a temporary closure of Tonbridge Walk.  Tonbridge Walk will  be closed over two periods.

  • The first closure will commence on 19 February to 12 March 2018.  The second closure will commence on 1 April to 22 April 2018.  This will allow us to complete our works safely whilst at the same time maintaining a clearer, safer neighbourhood.

 

Argyle Street Closure

 

  • We will be carrying out our specialist floor works on level 10  which will involve concrete being pumped from Argyle Street into the building. We have arranged with Camden Council  for a road closure on Saturday 20th January 2018 from 6am to 11.59pm. If the works are completed before the specified duration, this will change.

  • All noisy works will be undertaken between the hours of 8am in the morning and be completed by 8pm in the evening.

 