Due to the scaffolding on the West elevation being removed, McLaren have applied for a temporary closure of Tonbridge Walk. Tonbridge Walk will be closed over two periods.

The first closure will commence on 17 February 2018 to 12 March 2018. The second closure will commence on 01 April to 22 April 2018. This will allow us to complete our works safely whilst at the same time maintaining a clearer, safer neighbourhood.

 

Argyle Street Closure

 

We will be carrying out our specialist floor works on level 10, which will involve concrete being pumped from Argyle Street into the building. We have arranged with Camden Council for a road closure on Saturday 20 January 2018 from 6am to 11.59pm. If the works are completed before the specified duration, this will change.

 

All noisy works will be undertaken between the hours of 8am in the morning and be completed by 8pm in the evening.